What you need before you start
An estimate can only be as good as its inputs. Before any pricing, collect these from the enquiry, and write down what is missing so that it goes into the offer as an assumption or a question.
- The single-line diagram or the load list, with the rating and type of every feeder.
- The specification: voltage, frequency, fault level and its duration, IP rating, form of separation, busbar material, cable entry and ambient temperature.
- The approved makes for switchgear, meters and other components.
- The commercial terms: delivery, payment, taxes, freight, validity, tests and inspection.
Step 1: Read the enquiry and fix the basics
Read the whole specification once, not only the pages about your panel. Clauses that change the price are often elsewhere: a type-test report, a special paint shade, seismic bracing or third-party inspection.
Fix the basic data of the panel in one place. Every later step reads from it.
| Item | Why it matters to the price |
|---|---|
| Fault level, kA for 1 s | Sets the breaking capacity of every breaker, the busbar supports and the panel's own rating |
| Form of separation | Sets the sheet steel, the width of sections and the assembly time |
| IP rating | Sets gaskets, ventilation and the derating of busbars |
| Busbar material and current density | Sets the weight of copper or aluminium, often the largest single cost after breakers |
| Makes | Sets list prices and discounts for most of the bill of materials |
Step 2: Turn the load list into feeders
Each line of the load list becomes a feeder with a type and a rating. For a motor, find the full-load current, choose the starter type the specification asks for, and then pick the breaker, contactor and overload relay as a tested combination from the maker's coordination table.
37 kW at 415 V = 37 000 ÷ (1.732 × 415 × 0.93 × 0.86) = 64 A
Three things are easy to miss here:
- Type 2 coordination. If the specification asks for it, the components must come from the maker's Type 2 table for your fault level. A cheaper mix of parts is not Type 2.
- Spare feeders. Count the fully equipped spares and the empty spaces the specification asks for.
- What rides on each feeder. Ammeters, CTs, indicating lamps, local and remote selector switches and space heaters are small, and there are many of them.
Step 3: Size the incomer, the busbar and the fault rating
Add up the running load with the diversity the client allows, add the largest motor's starting needs if they ask for it, and choose the next standard incomer. The main busbar carries the incomer rating. Vertical busbars are sized for the load of their own section.
Check the fault rating against the source. A panel fed from a 1000 kVA transformer with 5 % impedance sees about 29 kA, so every breaker and the busbar system must stand at least that. The fault level calculator does this sum, and the guide to fault level explains it.
Step 4: Lay the feeders into sections
The enclosure cannot be priced until you know how many sections there are. Place the incomer, then the feeders, by module height into vertical sections, with cable alleys and a busbar chamber as the form of separation requires. The count of sections gives the length of the panel, the weight of sheet steel and the length of main busbar.
Leave this step out and guess the size, and both the enclosure and the busbar cost are guesses too.
Step 5: Build the bill of materials
List everything, in groups that match how you buy.
| Group | What is in it |
|---|---|
| Class A | ACBs, MCCBs, drives, soft starters and capacitors |
| Class B | Contactors, relays, meters, CTs, MCBs and accessories |
| Class C | Terminals, lamps, push buttons, selector switches, wiring and hardware |
| Busbar and supports | Main and vertical bars, links, joints, insulators and sleeves |
| Enclosure | Sheet steel by weight or a modular system, gland plates, doors, paint and gaskets |
Class C looks small on each feeder and is large in total. Count it per feeder type and multiply. Do not put in one lump sum.
Step 6: Price it
Price each line from your own list prices less your own discount for that make and class. Copper and aluminium go in at the day's rate by weight. Then build up to the offer price in clear layers.
- Material cost, by group.
- Contingency on material, for what the enquiry leaves unclear.
- Labour: fabrication, assembly, wiring and testing.
- Overheads and margin.
- Packing and transport.
- The offer price before tax, and then GST.
Decide once whether your percentage is a markup on cost or a margin on the selling price, and use it the same way every time.
Cost 100, margin 20 % → price = 100 ÷ 0.80 = 125
Step 7: Check before you quote
- Every breaker's breaking capacity is at or above the fault level.
- The busbar size, the supports and the temperature rise suit the rating and the IP.
- Quantities in the estimate match the single-line diagram, feeder by feeder.
- No item is still at a placeholder price.
- Deviations from the specification are listed in the technical offer, not left for the client to find.
- The validity of the offer is no longer than the validity of your metal and switchgear prices.
Where estimates go wrong
- Pricing from the feeder count alone. Two panels with the same feeders can differ widely because of form, IP and fault level.
- Forgetting the neutral and earth bars, busbar joints, shrouds and supports.
- Old metal rates. A copper rate from last quarter can remove the margin on a busbar-heavy panel.
- Unpriced tests and documents. Type tests, inspection visits and drawings for approval all cost time.
- One total with no breakdown. When the client negotiates, you need to know which part of the price can move.
This guide describes a method. Selections must be confirmed against the maker's catalogue and IS/IEC 61439 for the actual job.
Questions people ask
How do I get the motor current from the kW rating?
Current = kW × 1000 ÷ (1.732 × voltage × efficiency × power factor). A 37 kW motor at 415 V with 93 % efficiency and a power factor of 0.86 draws about 64 A. For selection, use the maker's motor data and coordination tables, not a rule of thumb.
What is the difference between margin and markup?
Markup is added to the cost: a cost of 100 with 20 % markup sells at 120. Margin is a share of the selling price: a cost of 100 with 20 % margin sells at 125, because 100 ÷ 0.8 = 125. Mixing the two is a common reason an estimate earns less than planned.
How much contingency should I keep?
There is no fixed figure. It depends on how complete the enquiry is and on how long your prices hold. Keep it as its own line in the estimate, so that it can be discussed and reduced openly, and not hidden inside rates.
Copper or aluminium busbars?
The specification decides first. Aluminium is lighter and cheaper for the same current but needs a larger section and care at the joints. Copper is chosen where the specification asks for it or where space is tight.