Guide · batch optimisation

The golden batch: what it is, and how to find it in your own data

Every plant remembers a batch that ran better than the rest. The golden batch is the way of running that produced it, found on purpose and repeated. You can start looking with the history you already keep.

What the golden batch is, and is not

A batch plant makes the same product again and again, and the results vary: yield, energy, time, chemical use. The golden batch is the way of running that gives the best result the plant can repeat, with every quality limit met.

It is not the best batch on record. One outstanding batch is usually part skill and part luck: good raw material, a cool day, a clean filter. Copy its settings on an ordinary day and you may get an ordinary result, or a batch out of specification.

What you want is what the good batches have in common, and that can be found.

What to collect

One row for each batch, with four kinds of column. A historian is the easiest source, but SCADA reports, batch sheets and a shift log in Excel serve as well.

Kind of columnExamplesWho controls it
SettingsSetpoints, dosing rates, speeds, hold times, recipe valuesThe operator or the recipe
ConditionsRaw-material analysis, ambient temperature, feed qualityNobody on the shift
ResultsYield, energy per tonne, batch time, chemical per unitThe outcome you want to improve
QualityTurbidity, COD, purity, strength, with their limitsMust be met, whatever else happens

Keeping settings and conditions apart is the most important step. Only settings can be changed tomorrow.

Finding it, in five steps

1. Remove the batches that failed quality

A batch with a record yield and an impurity over the limit is not a candidate. Take out every batch that broke a quality limit before ranking anything.

2. Rank what is left by one result

Choose the result that matters most, such as energy per tonne. Sort the batches by it and mark the best fifth or so as the good group.

3. Compare the settings of the good group with the rest

For each setting, look at the range the good batches ran in and the range of the others. Where the good group sits in a narrow band and the others are spread, you have a candidate. Where both groups look the same, that setting is not what made the difference.

4. Rule out luck

Check the conditions in the same way. If the good batches all had richer feed, the feed made them good and no setting will repeat it. Compare batches that had similar conditions, and see whether the setting still separates good from ordinary.

5. Write the golden batch as bands, not points

The result is a band for each important setting, for example "dosing between 42 and 46 litres per hour", and for a timed batch a path the key measurements should follow. A band can be held. A single number cannot.

Prove it with a trial

History shows what went together, not what caused what. Before the recipe changes, test the finding.

  1. Change one setting, by one modest step toward the band.
  2. Run enough batches at it to see past the normal scatter. Decide the number before you start.
  3. Compare the trial batches with the batches before, on the result and on every quality figure.
  4. If it worked, keep it and take the next step. If not, go back.

Decide in advance what result will make you stop and return to the old value. A trial without a stopping rule tends to run until someone is embarrassed.

Where it goes wrong

  • Too few batches. With twenty rows, almost any pattern can appear by chance.
  • Changing several settings at once. If the result improves, nobody knows which change did it.
  • Seasons. Summer batches compared with winter batches measure the weather.
  • Chasing one result. The lowest energy at the cost of batch time may not be the best plant.
  • Leaving limits to the software. The allowed range of every setting belongs to the process engineer. An optimiser works inside it.

Keeping the PLC in charge

None of this needs software inside the controller. The PLC holds the settings and enforces the interlocks. The analysis only decides what the settings should be, and that can happen at a desk. When the advice is later connected to the plant, the safe arrangement is for the PLC to hold each proposal inside fixed limits and for the operator to accept it.

This is the work the batch optimiser in Prakriya is being built to do: score the batches, separate settings from luck, propose a step inside your limits, and check afterwards whether the change worked.

Questions people ask

What is a golden batch?

It is the set of operating settings, and the path through the batch, that gives the best result your plant can repeat while meeting every quality limit. It serves as the reference that later batches are run against.

Is the golden batch just my best batch ever?

No. A single best batch often owes its result to things nobody controlled, such as unusually good raw material. The golden batch is built from what many good batches have in common.

How many batches do I need?

Enough that the good ones are a group and not a handful. Three to six months of regular production is a sensible start. With very few batches, treat any finding as something to test, not as a fact.

Does this apply to continuous plants?

Yes, if you treat each shift or day as one row. The same method then finds the settings behind the best shifts.